CHEKU WATER PROJECT DAILY REPORT, ON 31 ST JULY 2009. The Village Executive Officer called a village meeting, the village meeting should be held on 26thJuly 2009, I asked the Cheku village Officer to move forward the meeting due to my absent by that date. The village meeting forwarded to on 28 July 2009 by […]

JULY 14, 2009

CHEKU WATER PROJECT REPORTS On 14th July’09 the hemmer bit arrived from Dar-es-Salaam, late in the evening. On 15th July’09 the hemmer bit sub member didn’t fit to the drilling pipes, so Mr. Beda took it to Kondoa town for repair in order to fit with the drilling pipes. He came back by the day […]

JULY 13, 2009.

CHEKU WATER PROJECT DAILY REPORT ON 13 JULY 2009. From morning at 09:00a.m the drilling started by cleaning the WELL, the exercise was so hard due to the well being stopped for many days, walls of the well falling into the well so caused the work to be more hard. By using drug bit the […]

May 6, 2009

Hello. No doubt that everyone is fine, I am very fine too. The drilling- today on 05thMay’09. As I reported early that Mr. Beda a senior driller from Mr. Wilson’s company, he came to Kondoa for the picking money for buying fuel, he picked the money around at 11:45a.m, my friends in Kondoa helped him […]

Day 41 (May 5th, 2009)

Hello. I am very fine and hoping that everyone is fine too. Today on 4thMay’09- I and Mr. Bago we depart Kondoa town at 09:36a.m, as we agreed yesterday with Mr. Beda- a driller, he phoned us at 09:18a.m just about the rig problem were solved, asked us to go to the project site for […]

Day 40 (May 4th, 2009)

Hello Hoping that everyone is fine. I am very fine too. Today on 3thMay’09 we left Kondoa at 07:00a.m, by 08:20a.m we arrived at the Cheku project site. Refer my last email, official they drilled 26 meters deep and stopped there, they just waiting me and Mr. Bago to arrive at project site for further […]

Day 28 (April 22, 2009)

For the past 2 weeks Toni, the lead engineer, has been in India getting a part for the rig. During this time Moshi returned to Arusha and Mr. Bago to Dodoma. Toni went to India and returned with 2 technicians from to help repair the rig. Currently they are in Cheku with the water team […]

DAY 15 (April 9, 2009)

We are still waiting to a part come in from India. We must remember that this is Africa and things happen at a different pace. As a side note: Our MLA’s mentioned of our project in legislature: http://www.leg.bc.ca/hansard/38th5th/h90323p.htm#14534

DAY 10 (April 2nd, 2009)

Yet another delay. Hello. Myself, I am fine and hoping that everyone there is fine too. Depart in Kondoa. I and Mr. Bago left Kondoa an early at 07:a.m since we agreed to leave early and arriving early at the water project site. We arrived at the water project site early for drilling start. Water […]