CHEKU WATER PROJECT DAILY REPORT, ON 4 AUGAST 2009.
The drilling started at 08:30a.m, everything was moving very fast soon the drilling work reached 63 meters deep, the 3 meters was not yet cleaned by then. Exactly 61 meters was cleaned.
At 11:00a.m once again break down happened, this time corn Bering of the Mud pump, so the drilling stopped.
On 5 July’09 a driller- Mr. Beda traveled to Dodoma especial for repair the corn bearing.
I called him the next day, on 6 July’09 he told me that, he succeeded to repair the problem, and he was looking for the spear of corn bearing, soon he will find it, he might take a late bus back to Kondoa.
Moshi R. Changai
PROJECT MANAGER
CHEKU WATER PROJECT
(In Country Representatives)