Reserve your spot now!

Lara Kroeker Interactive

JULY 13, 2009.

CHEKU WATER PROJECT DAILY REPORT ON 13 JULY 2009.

From morning at 09:00a.m the drilling started by cleaning the WELL, the exercise was so hard due to the well being stopped for many days, walls of the well falling into the well so caused the work to be more hard.

By using drug bit the well cleaned deep to 39 meters, zone of 20 meters to 36 meters seems was been falling down. Walls of the well protected with cases down to 39 meters.

Since the exercise being harder, the hemmer bit was to be implemented, there was so hard due to the clay falling into the well, real cleaning the well was very hard, Final the exercise went in a proper way.

The Rig has no problems, driller as well worked very hard on this day.

My comments the work was excellent, and the local community was so much exited with work too.

Moshi R. Changai
PROJECT MANAGER
CHEKU WATER PROJECT
(In Country Representatives)