CHEKU WATER PROJECT DAILY REPORT, ON 3 AUGAST 2009.

This day the drilling started very late in the evening, at 16:38hrs, this because of the driller arrived at afternoon from Kondoa town where he had been fixing the piston shaft.

He took them several hours to replace the tool to the mad pump and then drilling started by the time mentioned above.

Only 1 meter drilled, now our WELL is 57 meters down. Technical the well has not any problem for the moment. The only problem for drilling is moving very slow, especial the happen down of the break down, in case no more break down the work will move very fast, and the work get finish soon.

Since the mad pump has no any problem, I hope the drilling will start early tomorrow on 4thJuly 2009.

I talked to a driller the time we had been at site,he told me that, no doubt that the water will be found due to the symptoms by the drilling.

Moshi R. Changai
PROJECT MANAGER
CHEKU WATER PROJECT