Hello Thanks for everything, I hope that all of you fine, I am very fine too. Find the attached file above contain pictures report of Cheku water project. Lara, I know that you understand very well our environment and Africa life, we are facing electricity power location, so we are given electricity mid of the […]

September 15th, 2009

CHEKU WATER PROJECT REPORT ON 8 th SEP’ TO 12th SEP’2009. On 3rd Sep’09 late evening the new mud pump arrived from Dar-es-Salaam. By that day Mr.Beda asked me to be at a water project site. On 4 th Sep’09 the new mud pump setting and tried if can work good, late in the evening […]

August 4, 2009

CHEKU WATER PROJECT DAILY REPORT, ON 4 AUGAST 2009. The drilling started at 08:30a.m, everything was moving very fast soon the drilling work reached 63 meters deep, the 3 meters was not yet cleaned by then. Exactly 61 meters was cleaned. At 11:00a.m once again break down happened, this time corn Bering of the Mud […]

August 3, 2009

CHEKU WATER PROJECT DAILY REPORT, ON 3 AUGAST 2009. This day the drilling started very late in the evening, at 16:38hrs, this because of the driller arrived at afternoon from Kondoa town where he had been fixing the piston shaft. He took them several hours to replace the tool to the mad pump and then […]

August 2, 2009

CHEKU WATER PROJECT DAILY REPORT, ON 2 AUGAST 2009. The drilling started at 08:48a.m, the drilling performance was very good, from the previous 50 meters; they drilled more 6 meters deep. At 14:30hrs, they had break down to piston shaft, a driller took it to Kondoa town where it will be fixed. The drilling was […]

JULY 31, 2009.

CHEKU WATER PROJECT DAILY REPORT, ON 31 ST JULY 2009. The Village Executive Officer called a village meeting, the village meeting should be held on 26thJuly 2009, I asked the Cheku village Officer to move forward the meeting due to my absent by that date. The village meeting forwarded to on 28 July 2009 by […]

JULY 14, 2009

CHEKU WATER PROJECT REPORTS On 14th July’09 the hemmer bit arrived from Dar-es-Salaam, late in the evening. On 15th July’09 the hemmer bit sub member didn’t fit to the drilling pipes, so Mr. Beda took it to Kondoa town for repair in order to fit with the drilling pipes. He came back by the day […]

JULY 13, 2009.

CHEKU WATER PROJECT DAILY REPORT ON 13 JULY 2009. From morning at 09:00a.m the drilling started by cleaning the WELL, the exercise was so hard due to the well being stopped for many days, walls of the well falling into the well so caused the work to be more hard. By using drug bit the […]

May 6, 2009

Hello. No doubt that everyone is fine, I am very fine too. The drilling- today on 05thMay’09. As I reported early that Mr. Beda a senior driller from Mr. Wilson’s company, he came to Kondoa for the picking money for buying fuel, he picked the money around at 11:45a.m, my friends in Kondoa helped him […]